Tracking milestones on Purchase Orders and Work Orders

See when each step of a PO or WO is due and when it happened, and find late orders

Milestones show the key dates of a Purchase Order (PO) or Work Order (WO), from the day you issue it until the order is complete. Compare the date you agreed with your vendor to the date each step happened, and spot late orders at a glance.

Milestones are available on the Accelerate plan. To upgrade, go to Settings > Pricing plan and click Compare or upgrade.


The milestones

  • Issued: the Issue date of the PO or WO. To change it, change the Issue date in the document's Details.

  • Acknowledged: the day the vendor confirmed the order. When you send a PO or WO from Settle, the email has a link for the vendor. When they open it and click Acknowledge Document, Settle records the date. Point to that date to see Acknowledged by vendor. You can also enter the date yourself. See Send a PO to a vendor.

  • Production started: the day production starts.

  • Cargo ready: the day the goods are ready for freight pickup.

  • Shipped: the day the goods ship.

  • Arrived: the day the goods arrive.

  • Complete: the day the order is complete. You enter this date yourself.

Production started, Cargo ready, Shipped and Arrived belong to a shipment. If an order has more than one shipment, each shipment has its own set of these milestones. See Managing multiple shipments on Purchase Orders & Work Orders.


Contracted and actual dates

Each milestone has two dates:

  • Contracted: the date you agreed with the vendor.

  • Actual: the date the milestone happened.

The contracted dates of a shipment's milestones are its Production Start, Cargo Ready, Ship by date and Arrive by date. When you create a GRN for the order, Settle sets the actual date of Arrived to that day.

When an actual date is missing, Settle assumes the milestone happened on its contracted date. Add the actual date to confirm it.

When Settle records the Acknowledged date from the vendor's click, it shows that day in your own time zone. A date you enter yourself stays exactly as entered. See Time zones in Settle.


View and change milestones

  1. Open the Purchase Order or Work Order.

  2. On the Details tab, scroll to Milestones. On a draft, click Milestones to open the section.

  3. To change a date, click it in the Contracted or Actual column and pick the new date.

A change to a contracted date also changes the matching date on the shipment. You can't change Issued here, or the contracted date of Acknowledged.

Milestones section of an open purchase order, with the tooltip Delayed by 4 days on Cargo ready

The current milestone also shows at the top of the PO or WO, next to its status. Point to it to see all the dates.

Milestone states

The icon next to each milestone shows its state. Point to the milestone to read it:

  • Planned: the contracted date is today or later, and there is no actual date yet.

  • Reached: the actual date is on or before the contracted date.

  • Delayed by a number of days: the actual date is after the contracted date. The milestone also reads, for example, "Cargo ready 4 days late".

  • No actual date: the contracted date has passed and there is no actual date. A dot shows in the Actual column.

  • No dates: the milestone has no contracted or actual date.

Issued and Acknowledged always show Reached. To see if the vendor acknowledged, point to the Acknowledged date.


Milestones on the Purchase Orders and Work Orders pages

The Milestone column shows each order's current milestone: the last one reached by today, using the actual date or, when it is missing, the contracted date. If an order has more than one shipment, a milestone counts only when every shipment has reached it.

Point to the milestone to see all the dates. You can change a date right there. If the current milestone has no actual date yet, a note says it is assumed to be reached on the contracted date.

Purchase Orders page with the milestone dates of PO-2221 open from the Milestone column

Find orders by milestone

  1. Above the table, click the filter icon (Filters), or press F.

  2. In Milestone, pick one or more milestones. The filter calls Complete Completed.

  3. Click Apply.

The table then shows the orders whose current milestone is one you picked. To find orders by the day the vendor acknowledged them, use Acknowledgment date in the same panel.

Filters panel on the Purchase Orders page with the Milestone list open