Split one purchase order (PO) or work order (WO) into several shipments when the vendor ships the items at different times or to different locations. Each shipment has its own dates, freight details and destination, and you receive each shipment on its own goods received note (GRN).
Before you start:
More than one shipment per order is part of the Accelerate tier. On other plans, Add shipment shows the upgrade options instead.
Your role needs Full access to Purchase Orders, Work Orders & GRNs. If Add shipment or Edit is turned off, point to it to see why.
Add a shipment
Every PO and WO starts with one shipment that holds all of its items.
Go to Purchase Orders or Work Orders and open the order.
On the Details tab, scroll down to Shipments.
Click Add shipment. Settle adds a second shipment and opens Set up Shipments.
Fill in the shipments
In Set up Shipments, each shipment has its own card: SHP 1, SHP 2 and so on.
Fill in the details of each shipment. The fields are listed below.
To split the order further, click Add another shipment.
Under Allocate inventory across Shipments, enter how many units of each item go in each shipment, in the SHP 1 Qty, SHP 2 Qty columns. A new shipment starts empty, so lower the quantities in SHP 1 by what moves to the new one.
Check Allocated Qty: it shows the units across all shipments next to the ordered quantity, such as 2400/2400.
Close the window. Settle saves your changes as you type.
Shipment details
Shipment # and Status: the status is On track, In transit or Received. You can choose Received only after the shipment has a GRN. Confirming receiving sets it for you.
Production Start, Cargo Ready, Ship by date and Arrive by date.
Freight vendor, Tracking number, Freight method and Incoterms.
Destination: the location that gets the shipment. You need it to receive the shipment.
Change or delete a shipment
With more than one shipment, the Shipments section shows a table with one row per shipment.
To open Set up Shipments again, click Edit under the table, or click ⋮ at the end of a row and choose Edit shipment.
To change a shipment's Status, dates or Tracking number quickly, click that cell in the table.
To delete a shipment, click ⋮ at the end of its row and choose Delete, or click the delete icon on its card in Set up Shipments. Deleting a shipment also archives its GRN. You can't delete an order's last shipment.
If you add items to an order after you split it, Settle doesn't put them in a shipment. Allocate them yourself, or the Shipments section shows that the shipments are short.
When quantities don't match
The units across all shipments should add up to the ordered quantity of each item. If they don't when you close Set up Shipments, Settle shows Allocated quantities mismatch. Choose one:
Update PO or Update WO: Settle changes the ordered quantities to match the shipments. On a PO, this also changes the PO total.
Adjust: go back and change the shipment quantities.
Keep mismatch: close the window and fix it later.
While the quantities don't match, the Shipments section of the order shows a warning, such as "Shipments exceed the order by 7 units across 1 item" or "Shipments are short 5 units across 1 item". Click Adjust to change the shipment quantities, or Update PO to change the order.
Receive a shipment
Each shipment gets one GRN, so you receive the shipments one at a time as they arrive.
Make sure the shipment has a Destination. Without one, Receive is turned off. To set it, click Edit under the Shipments table.
In the shipment's row, in the GRN column, click Receive.
Click Create GRN, or click Upload PDF file to add your own GRN. Settle copies that shipment's quantities into the GRN.
Check the received quantities, and click Confirm receiving.
After you confirm, the shipment's status changes to Received and its GRN column links to the GRN. When you've confirmed receiving on every shipment, the order's status changes to Closed. For each step of receiving, see Manually receiving POs.