Every purchase order (PO) in Settle has a status that shows where it is in your buying process. Labels are your own tags, such as "Rush" or "Q4 restock". Use them to group POs and find them later.
PO statuses
Draft: you are still preparing the PO. POs that you create or upload in Settle start as drafts.
In review: the PO is waiting for approval.
Approved: the PO has all the approvals it needs.
Rejected: an approver rejected the PO.
Open: you sent the PO to the vendor and are waiting for the goods.
Closed: you received all the goods.
Canceled: the order will not happen.
The Purchase Orders page has a tab for each status. The Archived tab holds the POs that you moved to the archive.
How to change the status
Open a PO.
On the Details tab, click the Status field.
Select the new status. Settle saves it right away.
If the Status field is grayed out on a PO that is not In review, you don't have permission to change that PO. Ask an admin on your team.
POs that need approval
When an approval rule applies to a PO, the bottom of the PO shows Approval required, and you can select only Draft or Canceled. You can also ask for approval on any draft PO without a rule.
Click Request approval at the bottom of the PO. The status changes to In review, and the Status field is locked.
When the approvers approve it, the status changes to Approved. You can then send it or set it to Open.
If an approver rejects it, the status changes to Rejected. Fix the PO and click Request approval again, or set it to Draft or Canceled.
To withdraw a request, click Cancel at the bottom of a PO that is In review. The PO goes back to Draft. Only the person who sent the PO for approval can cancel the request. If your business allows it, an admin can also click Override. To set up approval rules, see Creating and reviewing approval workflows.
When the status changes automatically
When you click Send PO to Vendor on a Draft or Approved PO, the Set PO status to Open after sending switch is on. Leave it on, and Settle sets the PO to Open after it sends the email.
When you receive a PO on a goods received note (GRN), Settle sets the PO to Closed. If the PO has more than one shipment, it closes when every item is received.
When you change the quantities on a GRN or archive it, Settle checks the PO again. If the PO's GRNs no longer cover every item, the system sets the PO to Open. As soon as they cover everything, it sets the PO to Closed.
Add labels to POs
A PO can have several labels. Bills and vendors use the same list of labels.
On the Purchase Orders page, point to a PO and select its checkbox. Select more POs if you want to label them too.
In the panel at the top, click the Label icon.
Select the labels that you want or create a new one. A dash in a checkbox means only some of the selected POs have that label. Click it once to add the label to all of them, and again to remove it from all of them.
Click Save.
To label one PO, open it and click the Label icon at the top of the PO.
Settle creates the label, adds it to the POs that you are labeling, and shows the list of labels again. Each label name can be used only once.
Rename or delete a label
In the Label window, click the pencil icon next to the label.
Change the name or the color.
Click Save.
To delete a label, click the pencil icon, then the trash icon. Settle deletes the label right away, without asking, and removes it from every PO, bill and vendor that has it.
Find POs by label
Labels show in the Labels column on the Purchase Orders page, and above the Status field on the PO.
Click a label on a PO to see all POs with that label.
To filter by several labels, click the Filters icon on the Purchase Orders page, or press F, and select them in Label.
To remove a label from one PO, click the X on the label on the PO.